Minimum product first. Position as of — · last updated — · the Archive phase is an estimate of 30 lane-days until its plan exists.
— of — lane-days done, weighted by status. The arrow is the change over the 7 days before.
A phase whose consumed days (filled) reach past its plan (dashed) is where time has gone. The bars say the same in a form that is easier to compare.
—
Percent complete counts each lane by its planned days times how far along it is (not started 0, being planned 0.1, being built 0.4, in final checks 0.8, landed 1). A lane in final checks for more than three days, or built for longer than one and a half times its plan, is flagged. Phases marked as coming after the minimum product are not needed for the first release.
Standalone copy generated 2026-11-03T17:21:19+1100 from the build state file; the figures refresh daily at 08:00.